← All bills

Int 0707-2011

Disclosure of project cost increases.

IntroductionEnactedCommittee on Contractsintroduced 2011-11-03Local Law 2012/018

Enacted as Local Law 2012/018.

Official record · Legistar

Agenda: 2011-11-03Passed: 2012-03-26Enacted: 2012-03-26
Committee on ContractsProcurement Policy Board, review of City procurement policies and procedures, oversight over government contracts, Mayor's Office of Contract Services and collection agency contracts.

How it compares

20% of similar bills passed

10 passed · 40 died

This bill: 131 days in committee

Similar bills: median 646 days · 69 days when passed

Sponsors (25)

Lifecycle

HeardHearing on P-C Item by Comm
2011-10-31 · Committee on Contracts
HeldP-C Item Laid Over by Comm
2011-10-31 · Committee on Contracts
HeardHearing on P-C Item by Comm
2011-10-31 · Committee on Technology
HeldP-C Item Laid Over by Comm
2011-10-31 · Committee on Technology
IntroducedIntroduced by Council
2011-11-03 · City Council
ActionReferred to Comm by Council
2011-11-03 · City Council
HeardHearing Held by Committee
2012-03-14 · Committee on Contracts
ActionAmendment Proposed by Comm
2012-03-14 · Committee on Contracts
ActionAmended by Committee
2012-03-14 · Committee on Contracts
AdvancedApproved by Committee
2012-03-14 · Committee on Contracts
AdvancedApproved by Council
2012-03-14 · City Council
ActionSent to Mayor by Council
2012-03-14 · City Council
HeardHearing Held by Mayor
2012-03-26 · Mayor
AdvancedSigned Into Law by Mayor
2012-03-26 · Mayor
ActionRecved from Mayor by Council
2012-03-26 · City Council

Votes (5)

Aye (5)
Darlene MealyRobert JacksonLetitia JamesMelissa Mark-ViveritoMichael C. Nelson

Heard at (5)

City Council · 2012-03-14 · 1:30 PM · Council Chambers - City Hall
Committee on Contracts · 2012-03-14 · 10:30 AM · 250 Broadway - Committee Rm, 14th Fl.
City Council · 2011-11-03 · 1:30 PM · Emigrant Savings Bank - 49-51 Chambers Street
Committee on Technology · 2011-10-31 · 10:00 AM · 250 Broadway - Committee Rm, 14th Fl.
Committee on Contracts · 2011-10-31 · 10:00 AM · 250 Broadway - Committee Rm, 14th Fl.

Attachments (13)

Full text
Be it enacted by the Council as follows: Section 1. Chapter 1 of title 6 of the administrative code of the city of New York is amended by adding a new section 6-133 to read as follows: § 6-133. Notification of project cost increases. a. For the purposes of this section, “agency” means a city, county, borough, or other office, position, administration, department, division, bureau, board or commission, or a corporation, institution or agency of government, the expenses of which are paid in whole or in part from the city treasury. b. If an agency that has entered into a contract for construction and/or services with a maximum expenditure of more than ten million dollars in connection with a project included in the capital budget enters into a contract modification or extension that results in a total revised maximum expenditure that exceeds the original contract maximum expenditure by twenty percent or more, the mayor shall notify the council of such contract modification or extension, including details of the basis for and scope of the estimated additional costs. c. Once such notification has been provided for a contract, any additional modifications or extensions of such contract that increase the maximum expenditure more than ten percent over the total revised maximum expenditure shall trigger new notification to the council. d. Notifications pursuant to this section shall be provided on a quarterly basis sorted by project within forty-five days of the end of the calendar quarter within which the comptroller registered such contract action. §2. This local law shall take effect ninety days after its enactment into law. SKM/ASP LS #1880 2/17/12