Int 1043-2016
Requiring that all new and substantially renovated buildings conduct blower door testing.
IntroductionFiledCommittee on Housing and Buildingsintroduced 2016-01-06
Filed — closed without being enacted.
Official record · Legistar
Agenda: 2016-01-06Passed: 2017-12-31
Summary
This bill would require that all new and substantially renovated buildings conduct a blower door test verified by an independent third party.
Committee on Housing and Buildings — Department of Housing Preservation and Development, Department of Buildings and rent regulation.
How it compares
26% of similar bills passed
13 passed · 37 died
This bill: 725 days in committee
Similar bills: median 627 days · 176 days when passed
Compared against 50 Introduction bills in Committee on Housing and Buildings.
Ranked by how closely each matches this bill's topic — closest first:
Int 0155-2018
Requiring that all new and substantially renovated buildings conduct blower door testing.
1429dFiled
Int 1459-2019
Standards for natural ventilation.
1037dFiled
Int 0159-2002
Requirements for high performance buildings.
615dFiled
Int 0184-2014
Allowable maximum heat loss through building walls.
1376dFiled
Int 1508-2019
Requiring that vents in elevator hoistway enclosures be closed to prevent air leakage.
997dFiled
Int 1277-2018
Preliminary inspections.
159dEnacted
+ 44 more comparable bills
Sponsors (2)
Lifecycle
IntroducedIntroduced by Council
2016-01-06 · City Council
ActionReferred to Comm by Council
2016-01-06 · City Council
ClosedFiled (End of Session)
2017-12-31 · City Council
Heard at (1)
City Council · 2016-01-06 · 12:00 PM · Council Chambers - City Hall
Attachments (2)
Full text
Be it enacted by the Council as follows:
Section 1. Chapter 3 of Title 28 of the administrative code of the city of New York is amended by adding a new article 318 to read as follows:
ARTICLE 318
BLOWER DOOR TESTING
� 28-318.1 Required blower door testing. For any building undergoing new construction or substantial improvement, as such term is defined in appendix G of the New York city building code, to determine building envelope air leakage the owner shall conduct a blower door test that is verified by an independent third-party who is approved by the department. Such owner shall report, in a form developed or approved by the department, the results of each blower door test to the department no later than 90 days after the completion of such test. The department shall adopt rules and/or reference standards governing such blower door tests.
� 28-318.1.1 Reporting on blower door testing. The department shall make publicly available online in a non-proprietary format that permits automated processing the following information, at a minimum, for each blower door test result received by the department:
1. The date of such test;
2. The borough, block and lot number, and street address, of the building upon which such test was conducted;
3. The envelope air leakage of such building as indicated by the results of such test;
4. The floor area of such building; and
5. The main use or dominant occupancy of such building.
� 2. This local law takes effect 120 days after it becomes law, except that the commissioner of buildings shall take such steps as are necessary for its implementation, including the promulgation of rules, prior to such effective date.
LS# 3538
JCH
11/30/15 9:12AM
1